Ministry of Railways has planned to electrify balance Broad Gauge (BG) routes of Indian Railways (IR) by December, 2023.
The time line for completion of Electrification of entire BG routes of IR is as under:
Year
Target (Route Kilometre)
2019-20
6,000
2454 route kms achieved upto 01.01.2020
2020-21
6,000
2021-22
6,000
2022-23
6,500
2023-24
(upto Dec-23)
4,310
Total
28,810